Yes. Every house demolition in Brisbane needs building approval, which you get through a licensed private building certifier. If the house was built in or before 1946, and especially if it sits in Brisbane City Council's Traditional building character overlay, you may also need council planning approval, and that is not guaranteed. Check both before you sign a demolition or build contract.

What is building approval for a demolition?
Building approval is the permit that says the demolition can go ahead safely. Brisbane City Council's guidance is that you arrange it through a licensed private building certifier, and you give the certifier scaled, detailed plans prepared by a draftsperson or architect.
Your demolition contractor or builder will often coordinate this for you. Ask who is lodging it and what is included in the price, because certifier fees are usually extra to the demolition quote.
When does Brisbane City Council need to approve it too?
Planning approval is separate from building approval. Brisbane City Council protects many homes built in or before 1946 through its Traditional building character overlay and pre-1911 building overlay. Demolishing one of those houses can need a development application assessed against council's demolition code.
Those applications are judged on whether the house contributes to the character of the street, and some are refused. Several refusals have gone to the Planning and Environment Court, with cases from Kedron, Coorparoo, Albion and Wynnum among them. If your house is a pre-war Queenslander or worker's cottage, find out where it stands before you plan around a knock-down.
What can you demolish without planning approval?
Brisbane City Council says these don't need planning approval:
- A free-standing outbuilding built after 1946
- An internal wall or feature, or a stair
- A post-1946 addition or extension
- Post-1946 alterations removed to reveal the original design
Building approval rules still apply separately. Check with your certifier for anything structural.
What about Ipswich, Logan, the Redlands and Moreton Bay?
Brisbane City Council's pre-1946 rules only apply inside the Brisbane City area. Ipswich, Logan, Redland City and the City of Moreton Bay have their own planning schemes, and some have heritage or character controls of their own. Building approval through a private certifier applies everywhere in Queensland.
Which licences does the demolition contractor need?
Asbestos comes out first, before demolition. In Queensland, removing more than 10 m² of bonded asbestos needs a business with a WorkSafe Queensland Class B licence, and friable asbestos needs a Class A licence. Demolition using load-shifting equipment such as an excavator, skid steer or crane needs a WorkSafe Queensland demolition work licence.
What order should you do things in?
A sensible order for a knock down rebuild:
- Check the build date and your property's overlays
- Get an asbestos inspection and demolition quotes
- Lodge any council planning application if one is needed
- Get building approval for the demolition through a certifier
- Book disconnections and drain capping
- Remove the asbestos, then demolish
Booking disconnections early matters. Power, gas, water and sewer must all be off, and the drains capped by a licensed plumber, before the machines start.
What you get for the price
The standard we ask of every contractor we refer you to
The contractor does the work, not us. Ask for each of these in your written quote and contract.
- The right WorkSafe Queensland licence for the job: Class A or B for asbestos, and a demolition work licence where machinery or other licensed demolition is involved
- Public liability insurance, with the certificate on request
- Asbestos identified (tested where unsure) and removed before the building comes down
- A written, itemised quote: demolition, asbestos, disconnections, disposal and site clean-up listed separately
- Building approval arranged through a private certifier before demolition starts
- Services disconnected and drains capped by licensed trades
- Asbestos waste wrapped, labelled and taken to a licensed facility, with the disposal receipt
- A level, clean site at handover
Asbestos dealt with first, and paperwork you keep
Any asbestos is removed by a licensed removalist before demolition. Ask for the asbestos removal paperwork, the clearance certificate where one applies, and the tip receipts.
Licensed, insured contractor, public liability certificate on request